The Town of Leesburg will be performing the following milling and paving work:

  • Monday 4/15:   
    • Brown Meadows in front of units 204 and 205  
    • North St at intersection with Brown Meadows,
    • regular work hours and off the road by 3:00pm
  • Tuesday 4/16:   
    • Brown Meadows in front of units 204 and 205  
    • North St at intersection with Brown Meadows,
    • regular work hours and off the road by 3:00pm
  • Wednesday 4/17: 
    • Dry Mill Road In Front of LC High School work to start around 9am and complete by 3:00pm,
    • Fairview Street at Normandy 3pm through 7pm,
    • **this will be 12hr day, but crews will be off of more heavily-travelled roads by 3:00pm.
  • Thursday 4/18:
    • Russell Branch Pkwy at Wegmans Intersection work to start around 9am and be complete by 3:00pm
    • Featherstone between Balls Bluff and Barksdale 3pm through 7pm,
    • **this will be 12hr day, but crews will be off of more heavily-travelled roads by 3:00pm.

 Please note - these dates and times are subject to changed based on weather and availability of materials and equipment. Please contact Brian Lloyd, Inspectors Supervisor, at 703-771-2782 for any questions related to these projects.