Water Pollution Control Facility Backup Generator project information from Fiscal Year 2020 Budget (Project No. 24NEW2)

Construction Start Date: Spring 2024FY20 WPCF Backup Generator

Estimated Completion Date: Summer 2024

Project Manager: Amy Wyks 703-737-7119

Project Description:  Installation of a backup generator at the Water Pollution Control Facility for system redundancy and reliability to allow for continued operations during emergencies. The project will evaluate inclusion of the Utility Maintenance Building for emergency power generation needs.

Project Updates:

As of August 6, 2019 - There is no funding for this project until Fiscal Year 2024.