Hospital Water Storage Tank Recoating and Rehabilitation

Print
Press Enter to show all options, press Tab go to next option

Jump to: Project Updates

Hospital Water Storage Tank Recoating and Rehabilitation project information from Fiscal Year 2019 Budget (Project No. 18001)

Construction Start Date: Spring 2018Hospital Water Storage Tank Aerial

Estimated Completion Date: Summer 2018

Project Manager: Amy Wyks 703-737-7119

Project Description:  The Hospital Water Storage Tank is a town‐owned tank located on Old Waterford Road adjacent to the Inova Hospital Cornwall facility.

Based on a recent inspection, the following improvements are required to extend the useful life of the Town's water tank:

  • Water blast and recoat the exterior tank and repainting of the interior roof
  • Replace aging valves and piping in the vault

The tank was previously painted in 2000 and re-inspection is performed at five year intervals.

Design Engineer: Hazen & Sawyer, P.C.

Project Updates:

As of March 18, 2019 - Design is underway.