Morven Park Road Sidewalk

Print
Press Enter to show all options, press Tab go to next option

Jump to: Project Updates

Morven Park Road Sidewalk project information from Fiscal Year 2020 Budget (Project No. 14301)

Construction Start Date: Fall 2020     Morven Park Rd Sidewalk Aerial

Estimated Completion Date: Fall 2021

Project Manager: Anne Geiger 703-771-2742

Project Description:  This project consists of constructing missing segments of sidewalk along the west side of Morven Park Road to provide a continuous pedestrian access route between West Market Street and Old Waterford Road.  The project will also improve drainage and provide a uniform roadway section by completing the curb and gutter on both sides of the street and extending the storm drain system.

 

Neighborhood Meeting & Resident Questionnaire:

On January 29, 2014 a meeting was held to update Morven Park Road area residents on the project. Below are links to information provided during the meeting. During the meeting, a questionnaire was provided to obtain input on the design. A summary of the questionnaire responses showed:

  • Sidewalk Location - Over 85% of the respondents supported a sidewalk on the west side and only the west side of Morven Park Road. The remaining responses were split between wanting sidewalks on both sides, preferring the sidewalk on the east side, or having no preference to the location.
  • Curb and Gutter - Over 70% of the respondents supported curb and gutter on both sides of Morven Park Road to eliminate the roadside ditches. About 15% of the responses indicated a preference for curb and gutter only on the west side, and about 15% preferred no curb and gutter.
  • On Street Parking - Over 84% of the responses supported no on-street parking in the areas of the new curb and gutter.
  • Acceleration of the Project - Less than 30% of the responses supported reducing the scope of the project by eliminating the curb and gutter in order to accelerate the construction.

The following information was provided as part of the meeting:
Public Meeting Presentation
Project Aerial 
Project Questionnaire 

Project Contracts:

  • Design Engineer - Whitman Requardt and Associates, LLP

Project Updates:

As of September 6, 2019 - Design is underway.