 We are in the process of reorganizing the Town of Leesburg website. If you reached a "Page Not Found . . ." result by following a search engine link, please try your search again, using the search box below. We apologize for any inconvenience, but hope you will find our reorganized website easier to use.

Evergreen Mill Road Widening

Print
Press Enter to show all options, press Tab go to next option

Jump to: Project Updates

Evergreen Mill Road Widening project information from Fiscal Year 2020 Budget (Project No. 15302) 

Construction Start Date: Spring 2022Evergreen-Mill-Aerial

Estimated Completion Date: Spring 2023

Project Manager: Karin Franklin 703-771-6674

Project Description:  Widen approximately 1.3 mile of Evergreen Mill Road from the Heritage High School entrance (south of Battlefield Parkway) to South King Street (Route 15).  The existing two-lane road will be widened to a four-lane street with sidewalk on one side and a shared use path on the other side.  The project will include utility relocations, curb, gutter, and storm drainage.

Project funding is primarily from  Northern Virginia Transportation Authority (NVTA), VDOT revenue sharing funds and Loudoun County.

Project Contracts:

Design Engineer - WSP USA Inc.

Project Updates:

As of May 7, 2020 - Design for this project is underway.  Loudoun County recently approved partial funding for the project, which includes funding to extend the project limits south to the frontage along Heritage High School.