Edwards Ferry Road NE Sidewalk Improvements project information from Fiscal Year 2020 Budget (Project No. 22NEW1)Edwards Ferry Rd NE Sidewalk Improvements Aerial

Construction Start Date: Spring 2021     

Estimated Completion Date: Fall 2021

Project Manager: Anne Geiger 703-771-2742

Project Description:  Replace approximately 0.25 mile of sidewalk along the north side of Edwards Ferry Road from west of Woodberry Road (near Dodona Manor) to Prince Street. The existing concrete sidewalk in this area is substandard in width and the adjacent curb in insufficient in height. The new brick sidewalk will be designed in compliance with ADA regulations and will be constructed to current standards to provide a safer walking environment.

Contracts:

  •  Design Engineer - christopher consultants, ltd. (formerly Paciulli Simmons and Associates, Ltd.)

Project Updates:

As of September 6, 2019 - This project was accelerated in the Capital Improvement Program to start this year.  Design is underway.