Battlefield Parkway – Route 15 to Dulles Greenway project information from Fiscal Year 2019 Budget (Project No. 07315)

 2018-03-Pic-1  2018-03-Pic-2

 

Construction Start Date: Winter 2016/2017  Estimated Completion Date: Summer 2018

Project Manager: Walid Quttaineh 703-737-7055 (Construction) / Tom Brandon 703-737-6067 (Design) 


Battlefield - Route 15 to Dulles Greenway Aerial Map

Project Description: The project includes construction of a 0.7-mile segment of Battlefield Parkway on new alignment between South King Street (Route 15) and Evergreen Mill Road (Route 621); and widening of the existing Battlefield Parkway to four lanes between Evergreen Mill Road and the Dulles Greenway. The new roadway will be a four-lane divided arterial roadway with parallel sidewalk and shared-use trail. The project will reduce congestion and improve traffic flow to Route 15. This segment will complete the continuous Parkway from North King Street to South King Street around the east side of Town.

The roadway was planned to be constructed as a two lane roadway initially, then widened to four lanes when funding became available. Recently, the Virginia Department of Transportation provided $11 million in funding for the project. This additional funding will allow the Town to construct the entire four-lane roadway under a single contract.

Project Documents:

The following information was presented during a public hearing that was held on June 6, 2013:

Project Contracts:

Design Engineer - Rinker Design Associates, P.C.
Construction Management - Alpha Corporation
Construction Contractor - General Excavation, Inc.

Project Updates:

As of November 2, 2018 - This project is substantially complete.  The contractor is currently performing punch list work.  On Monday, April 16th, a ribbon cutting ceremony was held and the new lanes of Battlefield Parkway were permanently opened to traffic.