Water Treatment Plant Electrical Upgrades
Project No. 23506
Project Start Date: Summer 2022
Estimated Completion Date: Fall 2027
Project Manager: George Brant 703-771-6743
Project Description: Evaluate and replace an existing main electrical switch gear and motor control centers (MCC) installed in 1980 to improve the power feed to the water treatment plant. Replace ancillary breakers that feed critical plant operation equipment. Upgrade electrical equipment to meet technology demands.
Project Updates: As of June 2025 - Project bids for construction were opened in late May 2025. Anticipated contract award in Summer 2025.