Water Treatment Plant Electrical Upgrades
Project No. 23506
Project Start Date: Summer 2022
Estimated Completion Date: Fall 2027
Project Manager: Andy Noland 703-737-7068
Project Description: Evaluate and replace an existing main electrical switch gear and motor control centers (MCC) installed in 1980 to improve the power feed to the water treatment plant. Replace ancillary breakers that feed critical plant operation equipment. Upgrade electrical equipment to meet technology demands.
Project Updates: As of March 2026 - Project expected to be complete in winter o f2027/2028. Construction contract awarded in Summer 2025 to RASCO, Inc.