Water Supply and Wastewater SCADA Systems Replacement

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Project No. 22504

Project Start Date: Summer 2022FY20 Water Supply SCADA Replace

Estimated Completion Date: December 2026

Project Manager: Stephen Gates 703-771-6742

Project Description: The Supervisory Control and Data Acquisition (SCADA) of the Town's water supply and wastewater systems were originally designed and installed in 2002. SCADA systems provide means to control all plant and system processes. The project includes a detailed analysis of the existing system, framework development and implementation that ensures a successful conversion to the new resilient system. The project provides greater security and efficiency of the utility treatment plants' process control network.

Project Updates: As of June 2025 - The procurement for both the SCADA software and the systems integrator has been successfully completed. The Town Council has approved the initial task order for the selected systems integrator. The integrator contract outlines a project duration of approximately 540 days to complete the full SCADA system replacement, including design, implementation, testing, and commissioning.