Project No. 28501

Project Start Date: Spring 2024Hogback Tank

Estimated Completion Date: Fall 2026

Project Manager: Andy Noland 571-246-2728

Project Description: This project will inspect and recoat the Town's Hogback water storage tank. Pending the outcome of an engineer's evaluation, structural repairs to the interior roof support of the tank may be necessary at this time as well. Hogback tank interior and exterior were last recoated in 2010.

Project Updates: As of March 2026 -Roof system replacement design is complete. Additional work as part of the project includes overcoat of the exterior paint systems and interior/exterior re-coating applications.