Water Storage Tank Recoating - Carr Tank II

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Project No. 25505

Project Start Date: Spring 2029Carr Tank 1 Complete

Estimated Completion Date: Fall 2030

Project Manager: Russell Chambers 703-771-2728, Andy Noland 571-246-5713

Project Description: This project will include recoating of the Town's Carr II water storage tank and perform minor modifications to interior draining system to enhance de‐watering and cleaning activities. Carr Tank II was constructed in 2009.

Project Updates: As of May 2025 - Design has been awarded to Kimley Horn. During the pre-design inspection of this tank it was determined that this coating project can be delayed three to five years. Re-evaluation will occur in three years.