Project No. 27501

Project Start Date: Spring 2024FY22 UT Water Stroage Tank Carr I

Estimated Completion Date: Summer 2026

Project Manager: Andy Noland 571-246-5713

Project Description: Based on a June 2024 inspection, this project will re-coat the Town's Carr I water storage tank and perform minor modifications to interior draining system to enhance de-watering and cleaning activities. Carr Tank I was last painted in 2010 (interior and exterior).

Project Updates: As of March 2026, a contract has been awarded to complete structural and coating system refurbishments for the tank should begin during late Spring. Anticipated complete of work is scheduled for the end of July.