Town of Leesburg, Virginia
Home MenuHome Popular Searches
Water Pollution Control Facility Solids Processing Improvements
Project No. 25502
Project Start Date: Fall 2023
Estimated Completion Date: TBD
Project Manager: Asmita Deshmukh
Project Description: During the last two decades the solids treatment process has remained relatively unchanged. However, water usage has been declining due to conservation and low-flow fixtures which causes an increase in solids concentrations of sanitary sewer flow. The Town's solids processing facilities have been impacted and a biosolids capacity analysis is underway to evaluate current system treatment capacities.
The project includes refurbishment of the anaerobic digester facilities, replacement of two gravity thickeners and construction of a third gravity thickener, replacement of a digested sludge storage tank, installation of a new flare, installation of new primary sludge screens, and associated electrical and controls work.
Project Updates: In March 2026,, the Town's engineering consultant submitted the 100% design drawings for the project. The advertisement for bid is planned for June 2026.