Water Pollution Control Facility Secondary Clarifiers Refurbishment

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Project No. 500640

Project Start Date: April 17, 2025

Estimated Completion Date: January 12, 2026

Project Manager:  Andy Noland 571-246-5713

Project Description: Secondary Clarifiers C & D are settling tanks that separate sludge form water and remove suspended solids and scum from the treated wastewater. The tanks were originally placed in service in 2008. The tank mechanical systems are nearing the end of their useful life and require replacement.

Project Updates: As of June 2025, Notice to Proceed April 17, 2025. Preconstruction Meeting April 17, 2025. As built measurements completed. Currently reviewing submittal documents.