Morven Park Road Crosswalk - West Market Street and Loudoun Street

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

                                                                           VALEESBURG_signup 

Morven Park Road Crosswalk - West Market Street and Loudoun Street project information from Fiscal Year 2026 Budget (Project No. 24303)

Morven Park Rd Crosswalk Aerial FY25

Project Start Date: Summer 2023

Estimated Completion Date: Winter 2025/2026

Project Manager: Tom Brandon, 703-771-2768

Project Description: This project includes constructing crosswalks across West Market Street and Loudoun Street, SW east of the Morven Park Road intersection. The project will include the upgrade of sidewalks and handicap ramps to meet current ADA standards and will provide accessible and continuous pedestrian access for residents in that area, including a connection to the Westgreen subdivision.  The crosswalks will include pedestrian-activated flashing beacon signage. This project will be constructed in coordination with the Morven Park Road Sidewalk Project. 

Project Contracts:

  • Design Engineer - Whitman, Requardt and Associates, LLP

Project Updates:  As of October 30, 2025 – At the meeting on October 28, 2025, the Town Council approved a resolution authorizing an offer to acquire the necessary easements for this project. 

Construction of the crosswalk is expected to begin once the Morven Park Road Sidewalk project is completed.  The estimated completion date for the sidewalk project is early January 2026. 

Interested in more details about the crosswalk? View design details.

For information about the sidewalk project View the Morven Park Road Sidewalk Project page.