Morven Park Road Crosswalk - West Market Street and Loudoun Street project information from Fiscal Year 2026 Budget (Project No. 24303)

Morven Park Rd Crosswalk Aerial FY25

Project Start Date: Summer 2023

Estimated Completion Date: Winter 2025/2026

Project Manager: Tom Brandon, 703-771-2768

Project Description: This project includes constructing crosswalks across West Market Street and Loudoun Street, SW east of the Morven Park Road intersection. The project will include the upgrade of sidewalks and handicap ramps to meet current ADA standards and will provide accessible and continuous pedestrian access for residents in that area, including a connection to the Westgreen subdivision.  The crosswalks will include pedestrian-activated flashing beacon signage. This project will be constructed in coordination with the Morven Park Road Sidewalk Project. 

Project Contracts:

  • Design Engineer - Whitman, Requardt and Associates, LLP

Project Updates:  As of January 12, 2026 – Construction of the crosswalk will begin once the Morven Park Road Sidewalk project is complete. The sidewalk project is currently estimated to be completed by the end of January 2026.

An informal invitation for bids for the crosswalk project is expected to open in February 2026, with construction anticipated to start in early spring 2026.

Interested in more details about the crosswalk? View the design details  or view the full design plan.  In the design plan, the yellow highlights indicate the crosswalk location, and the purple highlights show areas designated for ADA accessibility (Americans with Disabilities Act).

For information about the sidewalk project View the Morven Park Road Sidewalk Project page.