Lawson Road Pedestrian Crossing of Tuscarora Creek
Lawson Road Pedestrian Crossing of Tuscarora Creek project information from Fiscal Year 2026 Budget (Project No. 27401)
Project Start Date: Summer 2021
Estimated Completion Date: Fall 2026
Construction Project Manager: Rizwan Ishaq (703) 737-7055
Project Description: Tuscarora Creek has significantly deteriorated the low water crossing between two cul-de-sacs on Lawson Road. A new stream crossing will provide bicycle and pedestrian access to the W&OD Trail from residential communities. Bank erosion approximately 200 feet upstream of the crossing will be stabilized to reduce further bank loss.
Project Contractors:
- Design Consultant - RK&K
- General Contractor - WG Construction, Inc.
Project Meetings:
- Preconstruction community meeting presentation - February 3, 2026
- Meeting presentation - February 9, 2022
- Watch the recorded presentation
Project Updates: As of April 15, 2026 – The contractor has begun placing concrete for the base of the box culvert, marking an important step in keeping the project moving forward. Prior to this work, a water diversion system was installed on March 25, 2026, to allow excavation for the box culvert to begin. Substantial completion of this project is expected in November 2026, and the project remains on schedule.