Town of Leesburg, Virginia
Home MenuHome Popular Searches
Town Hall Parking Garage Structural Repairs
Town Hall Parking Garage Structural Repairs project information from Fiscal Year 2026 Budget (Project No. 23102)
Project Start Date: Fall 2022
Estimated Completion Date: Spring 2028
Project Manager: Doug Wagner 703-771-6671
Project Description: This project consists of three phases: Phase I consisted of the structural repairs (completed); Phase II is handrail repair on all three levels, joint sealant removal, and replacement on Levels 2 and 3 and resurfacing of Level 3 (underway); and Phase III is work on the stairwells to mitigate water intrusion, scheduled for Fiscal Year 2028. All work proposed was identified in a structural study report completed in Fiscal Year 2020 and the work was prioritized based on the findings.
Project Updates: As of July 21, 2025 - Phase II of the project is expected to begin in early to mid August 2025, and completion is estimated for spring of 2028.
