Town Hall Parking Garage Structural Repairs

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Town Hall Parking Garage Structural Repairs project information from Fiscal Year 2027 Budget (Project No. 23102)

FY22 GG Garage Repairs

Project Start Date: Fall 2022   

Estimated Completion Date: Spring 2033

Project Manager:  Doug Wagner 703-771-6671

Project Description:  This project consists of three phases: Phase I consisted of the structural repairs (completed); Phase II consists of joint sealant removal and replacement on Levels 2 and 3 and resurfacing of Level 3 (completed) as well as handrail repairs (to be completed in Fiscal Year 2027); and Phase III will include sidewalk repairs on all three levels (scheduled for Fiscal Year 2033 using budget remaining from prior fiscal years). All work proposed was identified in a structural study report completed in Fiscal Year 2020 and the work was prioritized based on the findings.

Project Updates: As of July 21, 2025 -  Phase II of the project is expected to begin in early to mid August 2025, and completion is estimated for spring of 2028.