Future Priority Projects

 

The following is a list of projects that are priorities for future inclusion in the Capital Improvements Program based upon funding availability and the priorities of the Town Council. Costs are estimates and are subject to change.

Project

Project Summary

Estimated Cost

Status

Church Street Improvements Phase II (07304)

Project includes extension of paved roadway approximately 200 feet towards the W&OD Trail to connect to future private development. The project includes construction of a Crescent District water feature at the southern end of Church Street adjacent to the proposed Waterford Development project.

$500,000

Awaiting progress of future private development

Edwards Ferry Road Sidewalk Replacement (West of Woodberry Road) (NEW) 

Replace approximately 550 feet of curb and brick sidewalk on the north side of Edwards Ferry Road west of Woodberry Road. The project will improve the sidewalk to meet current ADA and VDOT standards for sidewalk width and vertical separation between the sidewalk and travel lanes. The project is not intended to improve roadway geometrics or drainage to meet current standards.

$200,000-$300,000

Awaiting Funding

Edwards Ferry Road Widening Improvements (NEW)

Widening of the roadway by approximately 1,600 linear feet between Battlefield Shopping Center and Battlefield Parkway. This will complete Edwards Ferry Road as a four lane divided roadway between the Bypass and the eastern town limits (previously CIP project #10301)

$1,000,000

Awaiting funding

Ida Lee Soccer/Lacrosse Field No. 3 (01301)

Development of a third irrigated soccer/lacrosse field at Ida Lee Park. Plans are ready to be approved.

$400,000

Awaiting funding

Police Renovation and Expansion (NEW)

Renovation and expansion of existing Public Safety facility at Plaza Street. Estimate is based on completed space needs assessment.

$18,000,000

Awaiting funding

Potential Recreational Amenities 

Recreational amenities at various sites utilizing BAN and proffer funds. Potential amenities could include; skate park redevelopment, seasonal tennis bubble at Ida Lee, enhancements to the A.V. Symington Aquatic Center, a third soccer/lacrosse field at Ida Lee, or playground expansion at Ida Lee.

$250,000 - $300,000

Awaiting funding

Town Branch Improvements (10305)

Project to provide stream channel improvements to the Town Branch corridor. The purpose of the project is to alleviate flooding, and to support the Crescent District Master Plan and proposed Waterford Development project.

$2,000,000

Awaiting funding

Traffic Signal and Left Turn Lane at Catoctin Circle/Edwards Ferry Road Intersection (07303)

Traffic studies have shown that a traffic signal and additional turn lanes are warranted at this intersection. A Loudoun County proffer in connection with the courthouse expansion project will fund the traffic signal. This project also includes a left turn lane for westbound traffic from Edwards Ferry Road onto southbound Catoctin Circle. The timing of this project was established to coincide with the completion of the Lowenbach Street improvement project (Project Number 05303). Implementation of this project will be based on an analysis of the impact of opening the neighborhood streets.

$900,000

Awaiting completion of Lowenbach improvements

Veterans Park at Balls Bluff (02302)

Design and construction of public recreational facilities, a public access road, parking, boat launch, picnic areas, meadow, park pavilions and visitors’ center consistent with Park Master Plan.

$4,000,000

Awaiting funding

Customs and Border Patrol Office Space

Design and renovation of space located on the first floor of the terminal building.  Office space will be created and flex space that will be used only when needed by Customs and by airport tenants at other times.  FBOs at the airport that operate international flights have requested this project.        

$500,000

Awating
funding

 

 